On Now
Coming Up
  • Thu., Jun. 20, 2013 12:00PM - 1:00PM CDT Chiefs Live! Tune in every Thursday for Chiefs Live! with Kendall Gammon and Mitch Holthus.
  • Thu., Jun. 27, 2013 12:00PM - 1:00PM CDT Chiefs Live! Tune in every Thursday for Chiefs Live! with Kendall Gammon and Mitch Holthus.
  • Thu., Jul. 04, 2013 12:00PM - 1:00PM CDT Chiefs Live! Tune in every Thursday for Chiefs Live! with Kendall Gammon and Mitch Holthus.
  • Thu., Jul. 11, 2013 12:00PM - 1:00PM CDT Chiefs Live! Tune in every Thursday for Chiefs Live! with Kendall Gammon and Mitch Holthus.
  • Thu., Jul. 18, 2013 12:00PM - 1:00PM CDT Chiefs Live! Tune in every Thursday for Chiefs Live! with Kendall Gammon and Mitch Holthus.
  • Thu., Jul. 25, 2013 12:00PM - 1:00PM CDT Chiefs Live! Tune in every Thursday for Chiefs Live! with Kendall Gammon and Mitch Holthus.
  • Thu., Aug. 01, 2013 12:00PM - 1:00PM CDT Chiefs Live! Tune in every Thursday for Chiefs Live! with Kendall Gammon and Mitch Holthus.
  • Thu., Aug. 08, 2013 12:00PM - 1:00PM CDT Chiefs Live! Tune in every Thursday for Chiefs Live! with Kendall Gammon and Mitch Holthus.
  • Thu., Aug. 15, 2013 12:00PM - 1:00PM CDT Chiefs Live! Tune in every Thursday for Chiefs Live! with Kendall Gammon and Mitch Holthus.
  • Thu., Aug. 22, 2013 12:00PM - 1:00PM CDT Chiefs Live! Tune in every Thursday for Chiefs Live! with Kendall Gammon and Mitch Holthus.

News

New Arrowhead by the Numbers

Posted Jul 23, 2010

Interesting construction facts about The New Arrowhead

  • 10,850,299 linear feet of steel rebar were used on the project - equal to 36,168 football fields
  • 1,570 tons of steel were used in The New Arrowhead
  • 115,096,950 wet pounds of concrete were utilized in the renovation equaling 57.5 tons, or the weight of 10 apache helicopters
  • 1,147 days of construction from groundbreaking on July 25, 2007 to the grand opening on September 13, 2010
  • 1,978,000 hours of construction labor were devoted to the project
  • 1,000 construction workers, approximately the number of laboreres on site during the peak of the renovation process in the summer of 2009
  • 2,149 32-inch televisions would equal the size of the two ArrowVision HD video boards that measure 37 x 150 feet and 42 x 100 feet, respectively
  • 28,000-square foot Chiefs Hall of Honor showcasing exhibits and artifacts from the franchise's illustrious history
  • 231,000 gross square footage of the VIP Club Level equaling the size of the Nelson-Atkins Museum in Kansas City
  • 2,074 linear feet of digital ribbon board circling the stadium
  • 5,000-square foot team store, open year-round
  • 356 seats available for fans with disabilities, almost a 300 percent increase
  • 40-foot-wide concourses, large enough to park five semi-trucks side by side
  • 1,172 toilet fixtures, an 83 percent increase
  • 100 additional desktop work spaces for members of the media
  • 445 concession purchase points for fans, a 47 percent increase
  • 850 panels of glass were installed throughout the stadium
  • 22,134 trees and plants were landscaped on theNew Arrowhead grounds

 